Pipeline Extension Manda-Maweni

Total Budget

KSh 15,000,000.00

Funding Source
County Government
Ward
Shella Ward
Project Description

-Construction of 9.45km pipeline

-Materials for pipeline

-Concrete and masonry works

-Project administrative cost

-Construction and fabrication of 1 elevated steel water tank 50m3 capacity on 24m high tower

-Construction of 50m3 sump tank, Installation of solar pumping system

-Construction of chain-link fence 0.22km

-Construction of security house

Project Info
Project Name
Pipeline Extension Manda-Maweni
Project Status
Upcoming
Added On
07 Apr 2026